*Electricity and water connections in Mallorca — including the decisive finca/rústico specifics: no connection without a cédula, solar subsidies and the island's water scarcity.*
Legend: ✅ official/multiply documented · 🟡 municipality-/provider-dependent · 🔴 uncertain. Amounts are reference values (municipality-/tariff-dependent).
distribuidora) vs. supply (comercializadora): grid/meter/connection → e-distribución(Endesa group); tariff → a comercializadora. GESA is the historic Balearic company (today part of Endesa) — it still appears in old contracts. 🟡
Cambio de titular (change of account holder): with Endesa free of charge, ~15–20 working days. Alta(new connection) requires a valid boletín eléctrico/CIE (~70–300 €, valid for 20 years).
Potencia contratada (kW): determines the fixed costs; changeable at most 1×/year (except with acambio de titular).
15-minute pricing**. In 2025 PVPC was mostly cheaper than the free market. ✅
For buildings erected after 1.3.1987 without a permit and classed as fuera de ordenación, utilities may not provide a definitive connection without a valid cédula de habitabilidad (electricity/water/gas/telecoms). → On fincas without a cédula, a legal electricity connection is effectively blocked — a central check before buying (→ Ch. 09).
compensación simplificadafor installations ≤ 100 kW (surplus is offset in money against grid consumption, no payout). Installations up to 15 kW without an access/connection permit. ✅
rústico: PV for self-consumption on a legal finca counts as uso admitido(Art. 48 Ley 10/2019) — no DIG required; usually comunicación previa + registration with the CAIB energy authority (a prerequisite for compensation/subsidy). ✅
other municipalities up to 100 %); ICIO (Palma up to 95 %); Balearic subvenciones (Govern/IDI) also for batteries and aerothermal/heat pumps. Amount depends on the municipality → check the Ordenanza.
cambio de titular usually free of charge,~3–4 working days. Price ~2.52 €/m³ + fixed charge 🟡.
isolated fincas are not connected to the grid → self-supply via an aljibe/cisterna (cistern) + tanker (cuba/camión de agua). Water logistics is a real cost factor. ✅
pozo/sondeo): a permit from the CAIB (Recursos Hídrics) is required — **autorizaciónup to 7,000 m³/year (max. 1 l/s), above that concesión; meter mandatory** (RD 49/2023, Plan Hidrológico). Illegal wells are subject to penalties. ✅
fosa séptica/depuradora); **nocédula/first occupancy without an approved system**; illegal vertidos 600 €–600,000 €. ✅
Canon de saneamiento (Ley 9/1991): Balearic wastewater levy (fixed + consumption), collected via thewater bill and remitted to the ATIB. 🔴 Check the exact 2025 tariffs at the BOIB/ATIB.
Mallorca has no comprehensive natural-gas network. Common are butano/propano (bottle/tank, mainly Repsol/Cepsa) — plan for storage/delivery logistics; increasingly replaced by aerothermal + PV.
RD 390/2021: mandatory for sale/letting (scale A–G; valid 10 years, only 5 for G). Since August 2025 also required for the mortgage tasación ✅. The EU EPBD Directive 2024/1275 introduces minimum standards from 2030/2033 🟡. (→ Ch. 02)
Will I get electricity and water at every finca? No. For buildings erected after 1.3.1987 without a permit (fuera de ordenación), utilities may not provide a definitive connection without a valid cédula.
Do I need a DIG for solar on the finca? No — PV for self-consumption on a legal finca is uso admitido (Art. 48 Ley 10/2019); usually a comunicación previa + CAIB registration suffices.
May I simply drill a well? No — an autorización (up to 7,000 m³/year) or concesión from the CAIB is required, with a mandatory meter.
Ley 9/1991 (canon saneamiento) · RD 390/2021 (CEE) · EMAYA/ATIB/CAIB Recursos Hídrics